HYDROPOWER PLANTS constructed on the basis of the projects of JSC “HYDROPROJECT”

Name of HPP Channel

Flow rate of HPP m³/s

Installed capacity MW

Number of hydraulic units

Annual electric energy output, mln. kWh

Period of construction

Taligulyan №1 Dargom-Taligulyan tract 24 3 2 12 1943-1945
Ak-Kavak№2 Chirchik-Bozsu tract 90 9 2 66 1943-1946
Namangan №2 Yangi channel 18,5 1,2 1 9 1945-1947
Farkhad Syrdarya river 486 118,7 4 500 1943-1949
Shakhrikhan №6 Shakhrikhansay channel 48,4 11,4 2 72 1945-1949
Lower-Bozsu№2 Chirchik-Bozsu tract 73,5 7 3 15,4 1945-1949